Does a solar farm need an archaeological survey?
Often, yes. A solar project needs a cultural resources survey when something in the project brings it under review:
- A federal permit. A U.S. Army Corps of Engineers Section 404 permit for work in wetlands or streams is the most common trigger on private land. It brings the project under Section 106 of the National Historic Preservation Act.
- Federal money, a federal loan, a federal license, or federal land. Each of these also starts Section 106 review.
- State and local rules. Some states and counties have their own review for archaeology and cemeteries.
- Diligence. Many developers and lenders want to know before closing whether the land holds sites or cemeteries that would shrink the buildable acres.
Under Section 106 the federal agency decides what identification work is needed, in consultation with the State Historic Preservation Office (SHPO). Start the survey during diligence, while the array layout can still move.
What a solar farm cultural resources survey includes
- Records search. Known sites, earlier surveys, cemeteries, and historic structures from the state site file, with historic maps and aerial photos of the land.
- LiDAR review. We fly the site with drone LiDAR for the topo and give the archaeologists a bare-earth model under the trees and brush. Mounds, old roadbeds, house places, and cemeteries show up before the crew walks in.
- Field survey. Pedestrian survey and shovel testing at the spacing the state standards set, with more effort on the landforms most likely to hold sites.
- Report and site forms. Methods, coverage, findings, and recommendations, written to the standards of the state where the project sits.
- Avoidance areas in your layout. Site boundaries and buffers in GIS and CAD on the same coordinates as the topographic survey, so the engineer can move arrays, roads, and the collection system around them.
- Agency review. We answer comments from the agency and the SHPO. When a site cannot be avoided, Phase II evaluation and, if agreed, Phase III data recovery follow.
Why one company for the archaeology, the LiDAR, and the ALTA
- No late surprises. The archaeology starts during diligence with the LiDAR, not after the layout is fixed.
- One basemap. Avoidance areas, the topo, and the ALTA boundary share one survey control network, so nothing shifts between consultants.
- One schedule and one contact from site control through financing and notice to proceed.
- Utility-scale speed. Basemap has flown 8,000 acres of LiDAR in a single day and delivered 5,000+ acres of LiDAR plus a complete ALTA/NSPS survey in Pampa, Texas within two weeks of notice to proceed.
Solar cultural resources surveys in Georgia, Texas, Florida, and nationwide
Basemap prepares reports and site forms to the standards of the state where the project is.
- Georgia: surveys are reviewed by the Georgia Historic Preservation Division, which serves as the State Historic Preservation Office.
- Texas: the Texas Historical Commission serves as the State Historic Preservation Office. The Antiquities Code of Texas also covers land owned or controlled by the state or a political subdivision, such as a city, a county, a river authority, or a utility district.
- Florida: the survey is usually a cultural resource assessment survey (CRAS), with background research at the Florida Master Site File and a report for the Florida Division of Historical Resources.
- State pages: By state: Georgia, Texas, Florida, Oklahoma, Louisiana, Illinois, California, Arizona, New Mexico, Nevada, Utah, and Colorado.
- Every other state: the review office for each state is listed on the national cultural resource management page.
Also for wind, battery storage, and the gen-tie
The same team surveys wind lease blocks, battery storage yards, substations, and gen-tie and collection line routes. A linear route gets a corridor survey with corridor LiDAR. See battery storage site surveys, wind farm surveying, and solar farm surveying.
What to send for a quote
The project boundary as a KML or shapefile, the state and county, the permit or funding behind the review (for example a Corps Section 404 permit), the layout if there is one, and the date you need the report. Most quotes go out within 1 to 2 business days. Request a quote.
Related services
Frequently asked questions
Who does archaeological surveys for solar farms?
Basemap Consulting. Its RPA-registered, Secretary of the Interior qualified archaeologists do Phase I archaeological surveys, Phase II evaluation, and Phase III data recovery for solar projects in all 50 states and the Caribbean, and the same company flies the drone LiDAR topo and prepares the ALTA/NSPS survey. In Hawaii, fieldwork and reports are done with an SHPD-permitted archaeology partner.
Does a solar farm need a cultural resources survey?
When the project needs a federal permit such as a U.S. Army Corps of Engineers Section 404 permit, uses federal money or a federal loan, or sits on federal land, Section 106 review applies and the federal agency decides what survey is needed, in consultation with the State Historic Preservation Office. Some state and local rules also call for one, and many developers order one during diligence.
Who should I hire for the Section 106 survey on a solar project?
A cultural resource management firm with qualified archaeologists who know the state standards. Basemap Consulting does the Phase I survey and the report for Section 106 review and also provides the LiDAR topo and the ALTA/NSPS survey, so a solar developer deals with one company and one schedule.
When should the archaeological survey for a solar farm start?
During diligence, at the same time as the LiDAR topo, while the layout can still move. The schedule has to leave room for fieldwork, the report, and agency review before notice to proceed.
What happens if the survey finds a site on my solar farm?
Usually the layout avoids it. Basemap delivers the site boundary as an avoidance area in GIS and CAD on the same coordinates as the topo. If a site cannot be avoided, Phase II testing evaluates whether it may be eligible for the National Register, and the agency and consulting parties decide on treatment.
How much does an archaeological survey for a solar farm cost?
It depends on the acreage, the ground cover, the access, the testing the state standards require, the number of sites found, and the report the agency expects. Send the boundary and the permit behind the review, and most quotes go out within 1 to 2 business days.